Rio Grande Street: Contractor has been working on Rio Grande installing sidewalks and curb ramps at the northern corners of Ben Wilson Street. Contractor will begin working on sidewalks and driveways between Ben Wilson and Palm Drive starting Monday, June 29.
Navarro work: Contractor drilled and poured the foundations for the new traffic signal at Morning Glory.
Week of July 13-17: Contractor will begin pavement milling from Loop 463 south toward Huvar Street. Subcontractor will begin boring for new illumination poles from Loop 463 South.
Beginning July 20: Long-term lane closure will be installed beginning at Loop 463 and continue to Huvar Street. The inside lanes in each direction will be closed for approximately one month while the contractor installs the new concrete median.
Motorists should expect possible traffic delays and are urged to use caution when driving through the work zone.
For media inquiries, contact TxDOT Media Relations at MediaRelations@txdot.gov or 512-463-8700.